Kurrajong Road
Industrial
Factory development in 2022 for our valued client, spanning a total GFA of 1657 m2
Client
Duration
Location
completion
Hip Single Pty Ltd
12 Months
$2.3M
Prestons, Sydney
2022
Value
Client
Duration
Location
completion
Value
CIR Construction’s Roles and Responsibilities for this project included;
• Project and Construction Management.
• Coordination of all supervisors and trades on site.
• Construction scheduling of project and contract negotiations and administration.
• Fortnightly updates to client.
• Liaise with authorities and consultants to deliver OC on completion.